The F-35 Joint Strike Fighter (JSF) will cost much more than currently predicted, and the expected cost per flight hour already exceeds that of the F-16, according to the U.S. Government Accountability Office (GAO). In its latest annual report to Congress on the JSF, the GAO said cost and schedule pressures are mounting, and the development schedule “is likely to slip from 12 to 27 months.
The GAO did report progress in “several important areas,” but still repeated its previous view that production of the JSF is being ramped up too soon. In a previous story on the F-35 program, it was reported that Lockheed Martin and key manufacturing partners BAE Systems and Northrop Grumman were striving to drive down production cost.
But the GAO recently said Lockheed Martin adjusted the manufacturing schedule three times because of design changes, delayed parts deliveries and “manufacturing inefficiencies. According to the GAO, the first test aircraft required 35 percent more labor hours (65,000 more manhours) to build than planned.
This contradicts briefings that the program partners have given to the media, including AIN. Lockheed Martin and the F-35 program office in the Pentagon are preparing a new acquisition cost estimate, “which is expected to be much larger than what is now budgeted,” the GAO said.
|
A400M rescue goes past the wire
Wednesday 03. of February 2010 Airbus chief executive officer Tom Enders refused all comment on the A400M airlifter here yesterday as talks to continue the troubled project... |
||
|
Lockheed Martin insists F-35 program is just fine
Wednesday 03. of February 2010 If Lockheed Martin is to be believed, there’s not much wrong with the F-35 program. In a briefing here yesterday, vice president F-35 business... |
||
|
First Beechcraft T-6As Delivered to Iraqi AF
Wednesday 03. of February 2010 Hawker Beechcraft has delivered the first four of 15 Beechcraft T-6A military trainers scheduled to go to the Iraqi air force under the terms of... |
||
|
Unmanned helos eyed for cargo carrying role
Wednesday 03. of February 2010 Unmanned air vehicles for cargo duties have been studied for some years, but the current difficulties being experienced by U.S. and other forces... |
||
|
Chengdu’s J-10B Multirole Fighter on Trial
Tuesday 02. of February 2010 With J-10A production in full stride, Chengdu is working on integrating new technology, which may lead to an improved production aircraft. A... |
||