Boston Logan’s Runway 15R/33L Closed for Maintenance

AINalerts » May 1, 2012
May 1, 2012, 3:58 PM

The Massachusetts Port Authority has begun a seven-month closure of Runway 15R/33L at Boston Logan International Airport for resurfacing and to complete Runway Safety Area (RSA) construction at the departure end of Runway 15R. Following daily closures this month, the runway will be completely closed starting about June 15 through late September, ending with daily closures again in October and November. The enhanced RSA will extend the existing Engineered Material Arresting System (EMAS) bed to a total of 500 feet.

FILED UNDER: 
Share this...

Please Register

In order to leave comments you will now need to be a registered user. This change in policy is to protect our site from an increased number of spam comments. Additionally, in the near future you will be able to better manage your AIN subscriptions via this registration system. If you already have an account, click here to log in. Otherwise, click here to register.

 