Work Wraps on Van Nuys Runway Rehab Project

AINalerts » September 3, 2013
Aerobatics champion Sean Tucker in his customized Challenger biplane, performed the ribbon cutting at the reopening of Van Nuys Runway 16R last Thursday, signaling the end of the lengthy rehabilitation project.
September 3, 2013, 3:30 PM

California’s Van Nuys Airport celebrated the completion of a seven-month, $20.5 million renovation on its main runway late last week. Aerobatic pilot Sean Tucker sliced the ceremonial ribbon with the speeding wing of his Challenger biplane, officially opening the revamped runway to traffic.

The modernization project on 8,000-foot Runway 16R, the largest maintenance project at the Los Angeles-area airport in more than 50 years, began in February and included approximately 2,500 hours of construction time spread over 300 days. During this time, the runway was closed entirely for 10 full days and 26 nights, and operated with shortened lengths for an additional 65 days.

The improvements include asphalt overlay and partial reconstruction of the runway’s north, center and south sections; installation of a new blast fence at the run-up area; repairs to the existing concrete runway ends; repair and expansion of concrete shoulder pavements; high-speed exit light modifications; new embedded approach lighting; and new pavement markings. The project, which is expected to extend the life of the runway for at least 20 years, was completed on time and on budget, according to airport owner Los Angeles World Airports.

FILED UNDER: 
Share this...

Please Register

In order to leave comments you will now need to be a registered user. This change in policy is to protect our site from an increased number of spam comments. Additionally, in the near future you will be able to better manage your AIN subscriptions via this registration system. If you already have an account, click here to log in. Otherwise, click here to register.

 
X