Salina Airport Reopens Main Runway
Salina Regional Airport in Kansas has completed a renovation of the northernmost section of its primary 12,300-foot Runway 17/35.
Salina Regional Airport in Kansas has completed the first phase of its rehabilitation of 12,300-foot Runway 17/35. A second phase, which will see the milling and repaving of the remaining 7,500 feet, will begin in July and shut down the runway until September. (Photo: Salina Regional Airport)